VLST HDD SHORE APPROACH IN TAIWAN
During the last few months VLST has successfully mobilised to Taiwan for their challenging HDD Shore Approach Project.
TECHNISCHE SPEZIFIKATIONEN
Klient
Ausführungszeitraum
02/11/2020
Bohrungslänge(n)
Multiple lengths up to 642 m
Querschnitt der Bohrung(en)
800 mm HDPE
Aktivitäten
The project involved pipe pushing of 800 mm HDPE pipe with lengths up to 642 m. In 2020 the equipment will be set up, surface casing will be installed and HDPE pipe welding will commence. The drilling, expected to take up to 6 weeks of work in 247 rotation, will commence early 2021 on schedule.
Besonderheiten
This job will be done despite the restrictions and challenges imposed as a result of the worldwide Corona virus outbreak.