'innovators
by nature'

‘BUILDING ON A POSTAGE STAMP, IN NORTHERN OVERIJSSEL’

Wonderfully steered bundle drilling 3x Ø125mm, by foreman driller Andries using the Ditch Witch JT24 11 ton rig.

TECHNICAL SPECIFICATIONS

Client

Bam Infra Energie en Water – Noord Oost
Implementation period
October 2023

Bore Lenght

100 m

Bore Cross-section

3 x Ø 125 mm

Activities

It started with plotting the coordinates of the drilling plan, excavating the entry and exit points and initiating the pilot drilling process. Following successful pilot drilling, the reamer phase could begin. We installed the pipes one by one, because of the limited space available in the middle of a residential estate. It’s what we call a fantastic example of ‘building on a postage stamp’. We finished by suctioning a ‘string’ through the pipe, to allow the client to install the winch. It was time to clean up our mess and move onto the next job. The entire operation was completed without any issues, within a day.
Special Circumstances
This work was conducted in the middle of a residential estate.

VIDEO