CLOSED FRONT DRILLING AT SCHIPHOL – CONSTRUCTION OF SEWERS
Next time you need the toilet at Schiphol, give VLST a thought.
TECHNICAL SPECIFICATIONS
Client
Implementation period
November 2023
Bore Lenght
69 m
Bore Cross-section
GRP Ø 924 mm sewer pipes
Activities
Close Front Drilling of 69 metres was executed right next to our national airport. Fantastic trenchless drilling of 3 x 3 m and 10 x 6 m long GRP Ø 924 mm sewer pipes which will ensure that all runs well when nature calls. Proud of our team Niels, Mike, Franklin and Patrick who once again did fantastic work! And thanks to our partners with whom we are able to realise such amazing projects.
Special Circumstances
This project took place right next to Schiphol airport, close to an extremely busy traffic intersection.