CLOSED FRONT DRILLING AT SCHIPHOL – CONSTRUCTION OF SEWERS

Next time you need the toilet at Schiphol, give VLST a thought.

TECHNICAL SPECIFICATIONS

Client

Implementation period
November 2023

Bore Lenght

69 m

Bore Cross-section

GRP Ø 924 mm sewer pipes

Activities

Close Front Drilling of 69 metres was executed right next to our national airport. Fantastic trenchless drilling of 3 x 3 m and 10 x 6 m long GRP Ø 924 mm sewer pipes which will ensure that all runs well when nature calls. Proud of our team Niels, Mike, Franklin and Patrick who once again did fantastic work! And thanks to our partners with whom we are able to realise such amazing projects.
Special Circumstances
This project took place right next to Schiphol airport, close to an extremely busy traffic intersection.