2 DRILLING WORKS FOR CONSTRUCTION OF PRESSURE PIPELINES IN EMMEN
The new Prime Drilling GmbH #PD50 in action for our client Dusseldorp Infra, Sloop & Milieutechniek.
TECHNICAL SPECIFICATIONS
Client
Dusseldorp Infra, Sloop & Milieutechniek
Implementation period
November 2020
Bore Lenght
Initial bore 250 m | Second bore 700 m
Bore Cross-section
Both bores Ø 750 mm
Activities
Construction of a new pressure pipeline, for transport of water to the sewer purification plant. A section of the pipeline runs under the ring road and under the canal. We executed two directional drilling works for this purpose.
Special Circumstances
Second drilling under the canal.