2 HDD WORKS UNDER EXISTING RESIDENTIAL NEIGHBOURHOOD IN BEEK EN DONK

An inspection by the Dutch Water Board showed the existing pipelines in Beek en Donk (Noord-Brabant) to be in a poor state of repair.

TECHNICAL SPECIFICATIONS

Client

Dutch Water Board
Implementation period

Bore Lenght

920 m and 260 m

Bore Cross-section

Ø 500 mm

Activities

We replaced the pressure pipeline by conducting two directional drilling works of Ø 500 mm with length of 920 260 metres.
Special Circumstances
The challenge behind this project was that the drilling route had been designed to be executed under an existing residential, which will often offer various bottlenecks. Drilling must often also take place around bends.