'innovators
by nature'

MICROTUNNEL BORING AMSTERDAM RAI

In the vicinity of Amsterdam RAI, we were commissioned by Waternet to undertake a microtunnel boring. This was a connection for the relocation of a sewer for construction of a new hotel.

TECHNICAL SPECIFICATIONS

Client

Waternet
Implementation period
February 2018 / 2 weeks

Bore Lenght

24 m

Bore Cross-section

Ø 600 mm

Activities

Drilling under 3 large drinking water transport pipeline and a cable bed. The pipeline is approximately 600 millimetres with a total length of 24 metres.
Special Circumstances
This project was completed in a very short space of time (2 weeks).

VIDEO