RELOCATION OF CABLES IN WILNIS

Cables and pipelines needed to be relocated for the purpose of the new construction of a roundabout at the Lange Meentweg in Wilnis.

TECHNICAL SPECIFICATIONS

Client

Eljes Infrastructurele Werken
Implementation period
February 2018

Bore Lenght

261 m

Bore Cross-section

Activities

Van Leeuwen Trenchless Technology was commissioned by Eljes Infrastructurele Werken to relocate three glass fibre trajectories. Van Leeuwen Trenchless Technology was also commissioned by Adinf to design this 261 metre long directional drilling project.
Special Circumstances
There was very little space available to execute the drilling of this project. By applying smart solutions, the necessary space could be found for the successful execution of the work!