LARGE AND SMALL HDD WORKS IN DRACHTEN

In Drachten, we conducted 8 HDD drilling works for sewage water pressure pipelines.

TECHNICAL SPECIFICATIONS

Client

Pannekoek GWW
Implementation period

Bore Lenght

5 km

Bore Cross-section

1x Ø400mm

Activities

The total length of the route is approximately 5 kilometres.
Special Circumstances
Four drilling units were deployed simultaneously in order to minimise hinder and complete the project as quickly as possible. Van Leeuwen Trenchless Technology was also responsible for designing a number of drilling works.